The team at Prima Systems have been working hard to complete the work at the Norton Knatchbull School in Ashford.
We have finished fitting the grey, white and silver Steni cladding panels to elevations 2, 3, 4, 34 and the Main Hall. We're now working on the main entrance area where we are installing blue Steni Colour cladding panels before moving on to installing Trespa Meteon panels in satin white on the eyebrow pods which we aim to complete by the middle of July.
We've been on site with Logan Construction since February to install the windows, doors, curtain walling and cladding elements to the refurbished facade of the school. All works on site will be complete in time for the new school term.